Byrne Cortlandville Expansion Updates: Dec. 11, 2025

Our expansion at Byrne Cortlandville is coming along nicely!

This week, 3 silos will arrive for installation at Byrne Cortlandville. Construction has also begun on the block wall for the boiler room, and scaffolding has been erected adjacent to the wastewater management facility.

The Hayner Hoyt Corporation is making significant progress on the warehouse and truck loading dock addition at Byrne Cortlandville. The installation of interior piers of the foundations and insulated metal wall panels is underway. Soon, the building will be fully enclosed, allowing us to heat the building and begin interior finishes.

“We are honored to have been selected for this project and to have maintained a strong 45-year partnership with Byrne,” Hayner Hoyt said in a LinkedIn post.