Byrne Cortlandville Expansion Update: Sept. 26, 2025

Check out our recent progress on the Byrne Cortlandville expansion for the week ending Sept. 26, 2025:

  • Road Paving is mostly complete, and the new entry road will be open for use this weekend.
  • Phase A underground Plumbing and Foundation Walls
  • Raw Bay 1 Exit Closed through 10/1/25
  • Steel is positioned, and erection begins Monday, 9/29/25
  • Target 10/1/25 for Phase 2B Excavation and traffic all redirected away from Osbeck Road.
  • Scale Relocation next week
  • Silo pad extension is ready for concrete.