Check out our recent progress on the Byrne Cortlandville expansion for the week ending Sept. 26, 2025:
- Road Paving is mostly complete, and the new entry road will be open for use this weekend.
- Phase A underground Plumbing and Foundation Walls
- Raw Bay 1 Exit Closed through 10/1/25
- Steel is positioned, and erection begins Monday, 9/29/25
- Target 10/1/25 for Phase 2B Excavation and traffic all redirected away from Osbeck Road.
- Scale Relocation next week
- Silo pad extension is ready for concrete.